Construction of Road From Kg. Tuit to Kg. Mat Daling Jerantut, Pahang

Client:

Ministry Of Rural And Regional Development Malaysia

Project Status:

Completed

Project Cost:

RM 500 million

Services Provided:
  • Master planning
  • Investigation works
  • Detailed design
  • Preparation of contract documents
Scope Of Works:
  • Construction of a new 55km 2-lane-single carriageway road to the JKR R3 geometric standard.
  • Bridges construction works at specified location.
  • Ground treatment and slope protection works.
  • Drainage works including roadside drain, culverts etc